Notifications

Wildfires have resulted in evacuations in some communities. Learn more.

CB6 Highway Standard Plates – Active

Active standard drawings for ‘Standard Specifications for Highway Construction’ as well as planning, design and construction guidelines.

Explore pages in:

Overview

The following lists all current standard CB6 drawings. Last updated March 2022.

Superseded and obsolete drawings can be found at CB6 Highway Standard Plates – Inactive.

  • Drawing notes: Revision triangles shown on the standard drawings are used to show revisions in the general area of the drawing and may not necessarily show each revision separately. A single revision triangle may identify several changes in the standard drawing. Users should compare the new version of a drawing to the previous version to determine all changes.
  • January 2008 – MicroStation CAD files are no longer available for downloading.

Section 2 drawings – Grade construction

2.3 Drawings – Grading (including intersections and cross-sections)

Drawing No.Drawing DescriptionRevision No.Date
2.3.C22"T"-Intersection Treatment (Type Ia) (Two-Lane Highway) Feb/23/93
2.3.C23Intersection Treatment (Type Ib)  (Two-Lane Highway) Feb/23/93
2.3.C24B"T"-Intersection Treatment (Type IIa) Main Road Designation RAU-211.8-110 Feb/23/93
2.3.C24D"T"-Intersectional Treatment (Type IIa) Main Road Designation RAU-209-110 Feb/23/93
2.3.C25BIntersectional Treatment (Type IIb) Main Road Designation RAU-211.8-110 Feb/23/93
2.3.C25DIntersectional Treatment (Type IIb) Main Road Designation RAU-209-110 Feb/23/93
2.3.C26BIntersectional Treatment (Type IIc) Main Road Designation RAU-211.8-110 Feb/23/93
2.3.C26DIntersectional Treatment (Type IIc) Main Road Designation RAU-209-110 Feb/23/93
2.3.C27B"T"-Intersectional Treatment (Type IIIa) Main Road Designation RAU-211.8-110 Feb/23/93
2.3.C27D"T"-Intersectional Treatment (Type IIIa) Main Road Designation RAU-209-110 Feb/23/93
2.3.C28BIntersectional Treatment (Type IIIb) Main Road Designation RAU-211.8-110 Feb/23/93
2.3.C28DIntersectional Treatment (Type IIIb) Main Road Designation RAU-209-110 Feb/23/93
2.3.C29BIntersectional Treatment (Type IIIc) Main Road Designation RAU-211.8-110 Feb/23/93
2.3.C29DIntersection Treatment (Type IIIc) RAU-209-110 Feb/93
2.3.C30BIntersection Treatment (Type IIId) RAU-211.8-110 Feb/93
2.3.C30DIntersection Treatment (Type IIId) RAU-209-110 Feb/93
2.3.C31B"T"-Intersection Treatment (Type IVa) RAU-211.8-110 Feb/93
2.3.C31D"T"-Intersection Treatment (Type IVa) RAU-209-110 Feb/93
2.3.C32BIntersection Treatment (Type IVb) RAU-211.8-110 Feb/93
2.3.C32DIntersection Treatment (Type IVb) RAU-209-110 Feb/93
2.3.C33BIntersection Treatment (Type IVc) RAU-211.8-110 Feb/93
2.3.C33DIntersection Treatment (Type IVc) RAU-209-110 Feb/93
2.3.C34B"T"-Intersection Treatment (Type IVd) RAU-211.8-110 Feb/93
2.3.C34D"T"-Intersection Treatment (Type IVd) RAU-209-110 Feb/93
2.3.C56Major Road Intersection on Four Lane Divided Highway Mar/93
2.3.C57Minor Road Intersection on Four Lane Divided Highway Mar/93
2.3.C58Major-Minor Road Intersection on Four Lane Divided Highway Mar/93
2.3.C59Major "T" Intersection on Four Lane Divided Highway Mar/93
2.3.C60Minor "T" Intersection on Four Lane Divided Highways Mar/93
2.3.C61Rural Frontage Service Road Intersection on Four Lane Divided Highways Mar/93
2.3M2Geometric Guidelines and Paving Limits of Intersecting Roadways at Time of Grading and /or First Stage Paving of Highway2Mar/07
2.3M3Geometric Guidelines and Paving Limits of Farm (Residential) Accesses at Time of Grading and or First Stage Paving of Highway2Mar/07
2.3M3AGeometric Guidelines and Paving Limits of Field Accesses at Time of Grading and /or First Stage Paving of Highway Mar/07
2.3.M4Approach Treatment for Major Intersecting Roadways1Jan/99
2.3.M5Approach Treatment for Minor Intersecting Roadways2Mar/31/06
2.3.M5AApproach Treatment for Minor Access to Low Volume Rural Roads (Design Speed1Jan/2021
2.3.M21ALog Haul Intersection Type 1 Right Turn from Minor Road Jan/93
2.3.M21BLog Haul Intersection Type 2 Left Turn from Minor Road Jan/93
2.3.M21CLog Haul Intersection Type 3 Jan/93
2.3.M21DLog Haul Intersection Type 4a Jan/93
2.3.M21ELog Haul Intersection Type 4b Jan/93
2.3.M21FLog Haul Intersection Type 5a Jan/93
2.3.M21GLog Haul Intersection Type 5b Jan/93
2.3.M21HLog Haul Intersection Type 5c Jan/93
2.3.M21ILog Haul Intersection Type 6 Jan/93
2.3.M30Proposed Staged Construction for Traffic Accommodation1Mar/87
2.3.M34BRoadside Turnouts on Recreational Roads Jul/91
2.3.M39Ditch Block Nov/86
2.3.M46Temporary Pipeline Crossing for Haul Road May/83
2.3M47AMedian (Concrete Curb, Asphalt Surface)3Mar/31/06
2.3.M56Typical Cross-Section for Grade Widening3Dec/00
2.3.M57Typical Cross-Section for Grade Widening for Offset Guardrail Jul/95
2.3.M58Typical Cross-Section for Sideslope Improvement1Apr/98

2.4 Drawings – Culverts

Drawing No.Drawing DescriptionRevision No.Date
2.4M1Culvert Installation (Open-Cut Method)1March 31, 2022
2.4.M2Typical Reinforced Concrete Pipe Installation Through Side Entrances May/79
2.4.M3Typical Reinforced Concrete Pipe Installation (Rubber Gasket Joint) May/79
2.4.M5Typical Cross-Section of Reinforced Concrete Pipe Culvert Installation for Median Drainage Apr/79
2.4.M6Typical Cross-Section C.S.P. Median Drain Inlet1Jan/99
2.4.M8Typical Cross-Section C.S.P. Installation for Median Drainage Apr/79
2.4M9Details of Standard Sloped End Sections for Plastic Culverts3March 31, 2022
2.4.M14Typical Reinforced Concrete Pipe Installation (Rubber Gasket Joint) May/79
2.4.M15Typical Reinforced Concrete Pipe Installation May/79
2.4.M18Culvert Installation By Trenching Jun/95
2.4.M19Culvert Installation By Coring and Trenching Jun/95

2.5 Drawings – Riprap

Drawing No.Drawing DescriptionRevision No.Date
2.5M1Hand-Laid Riprap (Rock or Sacked Material)1March 31, 2022

2.7 Drawings – Underground electrical conduits

Drawing No.Drawing DescriptionRevision No.Date
2.7.M1Details of Underground Conduit Installation Mar/79
2.7.M2Typical Electrical Conduit Installation Dec/84

2.10 Drawings – Manholes, inlets and catch basins

Drawing No.Drawing DescriptionRevision No.Date
2.10.M1Storm Drain Grate (600 mm x 900 mm - Storm Drain Inlet)2Feb/85
2.10.M2Concrete Storm Drain Inlet (Std. 1.2 m - 600 x 900 mm Opening)1Feb/87
2.10.M3Concrete Storm Drain Inlet 1200 mm Rubber Gasket Reinforced Concrete Pipe1Feb/85
2.10.M41200 mm Diameter Precast Concrete Sump Drain1Dec/86
2.10.M5Storm Drain Grate (for 600 x 900 mm Opening - Linear Bars) May/79
2.10.M6Storm Drain Inlet (900 x 1200 mm Opening - 1.4 m Height)1Dec/86
2.10.M7Storm Drain Grate (900 x 1200 mm Opening - Linear Bars)1Feb/85
2.10.M8Concrete Storm Drain Inlet 600 x 900 mm Opening (Cast in Place)1Feb/85
2.10.M91200 mm Diameter Precast Concrete Manhole1Feb/85
2.10.M10Concrete Storm Drain Inlet (900 x 1200 mm Opening)1Dec/86
2.10.M11Storm Drain Grate (900 x 1200 mm Opening - with Cross Bars)1Feb/85
2.10.M12Concrete Storm Drain Inlet (Std. 1.2 m Height - 600 x 900 mm Opening)1Feb/85
2.10.M14Precast Reinforced Concrete Manhole (1050 mm Diameter) Jun/94
2.10.M15Storm Drain Inlet (Std. 1.2 m Height - 600 mm x 900 mm Opening)1Feb/85
2.10.M17Detail of Catch Basin with Side Inlet Frame and Cover1Feb/85
2.10.M18Types of Trench Bedding and Backfill for Storm Sewer May/81
2.10.M20Precast Reinforced Catch Basin Manhole (1050 mm Diameter)2Dec/86
2.10.M21Precast Reinforced Concrete Manhole1Feb/85
2.10.M22Typical C.S.P. Manhole for Sewer Larger than Riser1Feb/85
2.10.M23Precast Reinforced Concrete Storm Drain Inlet Frame and Cover (1220 mm Diameter)1Apr/85
2.10.M24Precast Reinforced Catch Basin Manhole (1050 mm Diameter) Jun/94
2.10.M25Storm Drain Inlet Frame and Grate1Oct/86
2.10.M26Storm Drain Inlet Frame and Grate1Oct/86
2.10.M26AStorm Drain Inlet Frame and Grate (AT and U Embossed) Feb/88
2.10.M27Manhole Frame and Solid Cover1Oct/86
2.10.M27AManhole Frame and Solid Cover (AT and U Embossed) Feb/88
2.10.M28 Precast Reinforced Concrete Storm Drain Inlet (900 mm Diameter)1Jun/94
2.10.M29Storm Drain Inlet Frame and Cover1Oct/86
2.10.M30Precast Reinforced Catch Basin Manhole (1050 mm Diameter)1Jun/94
2.10.M31Precast Reinforced Concrete Manhole (1200 mm Diameter) Jun/94
2.10.M32Storm Drain Inlet Catch Basin Frame and Cover for Semi-Mountable Curb Jun/94
2.10.M32ADetail of Catch Basin with Side Inlet Frame and Cover Jun/94
2.10 M33Storm Drain Inlet Manhole Frame and Cover for Semi-Mountable Curb Jun/94
2.10.M34Wheelchair Ramp Catch Basin Manhole Cover Dec/95
2.10.M35Details of Asphaltic Flume Drain Outlet (Renumbered from 3.11.M14)1Oct/98

2.12 Drawings – Fencing

Drawing No.Drawing DescriptionRevision No.Date
2.12.M1Class "A" Fence2Feb/02
2.12.M2Class "B" Fence3Feb/02
2.12.M2AClass "B" Fence (Modified Wire Spacing)3Feb/02
2.12.M3Class "C" Fence3Feb/02
2.12.M4Class "D" Fence3Feb/02
2.12.M5Class "E" Fence 5Nov 10
2.12.M6Position of Fencing May/93
2.12.M7Class "F" Fence3Jan/17
2.12.M8Class "G" Fence (Class B Fence with Modified Post Spacing)3Feb/02
2.12.M11Class "B" Fencing Details for Using Metal Stays1Oct/96
2.12.M12Median Cable Fence June/15

2.13 Drawings – Livestock guards

Drawing No.Drawing DescriptionRevision No.Date
2.13.M4Livestock Guard Range Type 3.05m Width1Jul/95
2.13.M5Livestock Guard Standard Highway Type 4.88m Width1Jul/95
2.13.M6Livestock Guard Standard Highway Type 6.1m Width1Jul/95
2.13.M7Livestock Guard Standard Highway Type 7.32m Width2Nov/99
2.13.M11Livestock Guard Standard Highway Type 9.145m Width2Nov/99

2.15 Drawings – Metal bin retaining wall

Drawing No.Drawing DescriptionRevision No.Date
2.15.M1Metal Bin Retaining Wall - Type II1Jul/86

2.18 Drawings – Concrete and/or corrugated steel storm sewer

Drawing No.Drawing DescriptionRevision No.Date
2.18.M1Storm Sewer Trench Bedding and Backfill1Mar/83

2.29 Drawings – Culvert extensions and culvert liners

Drawing No.Drawing DescriptionRevision No.Date
2.29.M1Plastic Liner Installation and Grouting within Existing Culverts1Jan/03

Section 3 drawings – Surfacing

3.4 Drawings – Pavement sections

Drawing No.Drawing DescriptionRevision No.Date
3.4.M1Typical Half-Section Asphalt Stabilized and Granular Base Course Apr/81
3.4.M2ADouble Seal Coat and Base Course at Intersection of Primary Highway with Secondary Road or Road Allowance1Apr/81
3.4.M7Typical Half-Section for Granular Base Course and Asphaltic Concrete Pavement Jun/80
3.4.M16Asphaltic Concrete Pavement and Granular Base Course Jul/81

3.9 Drawings – Cement stabilized base course

Drawing No.Drawing DescriptionRevision No.Date
3.9.M1Typical Half-Section for Cement Stabilized Base Course and Asphalt Stabilized Base Course Apr/80
3.9.M3Typical Plan and Half-Section Cement Stabilized Base Course and Asphalt Stabilized Base Course Farm Entrance Apr/80

3.21 Drawings – Double seal coat

Drawing No.Drawing DescriptionRevision No.Date
3.21.M1Typical Plan and Half-Section for Double Seal Coat and Base Course Farm Entrance (Renumbered from 3.11.M3A)1Oct/98

3.23 Drawings – Seal coat application

Drawing No.Drawing DescriptionRevision No.Date
3.23.M1Seal Coat Application at Intersections (Two-Lane Highways) Jun/94
3.23.M2Seal Coat Application at Intersections (Four-Lane Divided Highways) Jun/94

3.35 Drawings – Crack repair: mill and fill

Drawing No.Drawing DescriptionRevision No.Date
3.35.M1Crack Repair Detail Mill and Fill 2 Dec/02

3.50 Drawings – Asphalt concrete pavement

Drawing No.Drawing DescriptionRevision No.Date
3.50.M1Typical Cross-Section for Asphaltic Concrete Pavement (Renumbered from 3.11.M1)2Oct/98
3.50M2Paving Limits of Intersecting Roadways at Time of Final Paving or Pavement Rehabilitation of Highway2Mar/07
3.50M3Paving Limits of Farm (Residential) Accesses at Time of Final Paving or Pavement Rehabilitation of Highway2Mar/07
3.50M3APaving Limits of Field Accesses at Time of Final Paving or Pavement Rehabilitation of Highway Mar/07
3.50.M16Transverse Pavement Joints1Oct/98

3.52 Drawings – Milled rumble strips

Drawing No.Drawing DescriptionRevision No.Date
3.52.M1Continuous Milled Rumble Strips for Shoulders11Sept 10/21
3.52.M3Milled Rumble Strips for Stop Conditions5Sept 10/21
3.52.M4Milled Rumble Strips for Centreline7Sept 10/21
3.52.M5Milled Edge Line Rumble Strips with Continuous Pattern2Sept 10/21
3.52.M6TMilled Edge Line Rumble Strips with Gap Pattern
(0.2 m ≤ Shoulder Width
3Sept 10/21
3.52.M7TMilled Edge Line Rumble Strips with Gap Pattern
(0.6 m ≤ Shoulder Width ≤ 1.5 m)
3Sept 10/21
3.52.M8TMilled Edge Line Rumble Strips with Gap Pattern (Shoulder Width > 1.5 m)3Sept 10/21
3.52.M9TMilled Edge Line Rumble Strips with Gap Pattern (Roadway Width Sept 10/21

Section 4 drawings – Miscellaneous

4.1 Drawings – Asphalt curb, medians, traffic islands and flumes

Drawing No.Drawing DescriptionRevision No.Date
4.1.M5Standard Asphaltic Sign Island (60m of 50:1 Taper) Sep/79
4.1.M6Typical Half-Section Asphaltic Concrete Pavement with Asphaltic Drainage Curb2Feb/85

4.2 Drawings – Concrete curbs, gutters, sidewalks, medians and traffic islands

Drawing No.Drawing DescriptionRevision No.Date
4.2.M15Pipeline Protection Slab Aug/98
4.2.M16 Precast "F" Shape NCHRP 350 Test Level 3
2
Aug/10/11 
4.2.M31Concrete Curb and Gutter Through Transition Section of Curves1Feb/85
4.2.M43Standard Concrete Sign Island - with Conduit2Feb/85
4.2.M43AStandard Concrete Sign Island - with Conduit1Apr/85
4.2.M47Raised Median (150 mm Curb) Jun/94
4.2.M47AMedian (Concrete Curb, Asphalt Surface) 200 mm Curb3Mar/31/06
4.2.M48Median End Treatment for Concrete Curb Median2Mar/85
4.2.M48AMedian End Treatment for Concrete Median Mar/85
4.2.M53Median End Treatment for Concrete Curb Median1Jun/83
4.2.M56Concrete Median (150 mm Face)2Jun/85
4.2.M56BConcrete Median (150 mm Face) - with PVC Crossdrain3Jun/85
4.2.M69Reinforced Concrete Gutter Outlet (1200 mm Wide x 280 mm High) Oct/80
4.2.M70Poured In Place Reinforced Concrete Gutter Sep/80
4.2.M72Poured In Place Standard Curb and Gutter (150 mm Curb, 380 mm Gutter)1Jul/86
4.2.M73Median End Treatment (Solid Conc. - Bullet Nose on Base Course)1May/85
4.2.M73AMedian End Treatment (Solid Concrete - Bullet Nose on ACP)1Jun/85
4.2.M74Concrete Curb Median (Earth Fill) - 150 mm Face Feb/85
4.2.M75Poured In Place Standard Curb and Gutter1Jul/86
4.2.M76Precast Concrete Curb - (150 mm Parking Curb) Mar/90
4.2.M77Precast Concrete Curb (with Drainage Slots) Mar/90
4.2.M78Poured-in-Place Concrete Sidewalk May/88
4.2.M79Poured-in-Place Concrete Sidewalk - Comm. or Public Crossing May/88
4.2.M80Poured-in-Place Concrete Sidewalk - Private Crossing May/88
4.2.M82Poured-in-Place Monolithic Concrete Sidewalk Curb and Gutter (300 mm Gutter)1Mar/85
4.2.M83Rolled Monolithic Concrete Sidewalk - Curb and Gutter Mar/85
4.2.M84Monolithic Concrete Sidewalk - Curb and Gutter (380 mm Gutter)1May/88
4.2M86Concrete Sidewalk Ramp for Wheelchair or Bicycle on Tangent (Type 1)1March 31, 2022
4.2M87Concrete Sidewalk Ramp for Wheelchair or Bicycle on Curve (Type 2)1March 31, 2022
4.2.M88

Monolithic Concrete 

Sidewalk, Curb and Gutter (500 mm Gutter)

3Sept/19/11
4.2.M89Poured in Place Standard 150 mm Curb and 500 mm Gutter3Sept/19/11
4.2.M90Rolled Monolithic Concrete Sidewalk, Curb and Gutter (500 mm Gutter)3Sept/19/11
4.2.M92Typical Cross Sections Raised Median with Semi-Mountable Curb Jun/94
4.2.M93Monolithic Concrete Sidewalk, Curb and Gutter (250 mm Gutter) - Paving Stone Edging Dec/95
4.2.M95Sidewalks - Typical Cross Sections Dec/95

4.3 Drawings – Concrete barrier

Drawing No.Drawing DescriptionRevision No.Date
4.3.M1Reinforced Concrete Med. Barrier Curb - NJ Shape (610 mm Wide) - with Expansion Joint 1977
4.3.M1AReinforced Concrete Median Barrier NJ Shape1Apr/17/07
4.3.M2Reinforced Concrete Med. Barrier Curb - F Shape (9 Re-Bars) May/85
4.3.M2AReinforced Concrete Med. Barrier Curb - F Shape (6 Re-Bars) May/85
4.3.M3Slip-Formed Median Barrier - F Shape4Sep/14/07
4.3.M3ASlip-Formed Median Barrier - Half F Shape1Sep/14/07
4.3.M4Transition End Sec. for Reinforced Concrete Median Barrier Curb - F Shape2Oct/86
4.3.M5lsometric View of Transition End Sec. for Reinforced Concrete Median Barrier Curb2Oct/86
4.3.M12Precast Concrete Barrier NJ Shape1Apr/17/07
4.3.M14Plan Showing Dowel and Grout Details - NJ Type May/85
4.3.M14APlan Showing Dowel and Grout Details - F Shape May/85

4.6 Drawings – Toilets

Drawing No.Drawing DescriptionRevision No.Date
4.6.M1Double Toilet  Drawing Index, Elevations and Vault Details4Jan/13
4.6.M2Double Toilet  Typical Layout Plan 1 and Section4Jan/13
4.6.M3Double Toilet  Typical Layout Plan 2 and Section4Jan/13
4.6.M4Double Toilet  Floor Plan and Section4Jan/13
4.6.M5Double Toilet  Tank Plan and Sections4Jan/13
4.6.M6Double Toilet  Floor Slabs Layout and Sections4Jan/13
4.6.M7Double Toilet  Floor Heating Layout and Section4Jan/13
4.6.M8Double Toilet  Precast Panel A, B, F and G Details4Jan/13
4.6.M9Double Toilet  Precast Panel C Details4Jan/13
4.6.M10Double Toilet  Precast Panel D Details4Jan/13
4.6.M11Double Toilet  Sections, Details and Colour Schedule4Jan/13
4.6.M12Double Toilet  Sections and Details4Jan/13
4.6.M13Double Toilet  Stool Details and Fixture Layout3Jan/13
4.6.M14Double Toilet  Roof Sections4Jan/13
4.6.M14ADouble Toilet  Roof Framing Plan3Jan/13
4.6.M15Double Toilet  Grid-Power Electrical and Mechanical Layout Plan2Jan/13
4.6.M16Double Toilet  Solar-Power Electrical and Mechanical Layout Plan2Jan/13
4.6.M17Double Toilet  Mechanical Room Section (Grid-Power Electrical)2Jan/13
4.6.M18Double Toilet  Mechanical Room Section (Solar-Power Electrical)2Jan/13
4.6.M19Double Toilet  Solar-Power Container Building Sheet 12Jan/13
4.6.M20Double Toilet  Solar-Power Container Building Sheet 22Jan/13

Section 5 drawings – Materials

5.10 Drawings – Sampling valve

Drawing No.Drawing DescriptionRevision No.Date
5.10.M1Detail of Motor Transport Truck Sampling Valve Jan/80

5.15 Drawings – Supply of corrugated metal pipe

Drawing No.Drawing DescriptionRevision No.Date
5.15.M1Details of Standard Sloped End Sections for C.M.P. Round Culverts3Jul/17
5.15.M2 Details of Standard Sloped End Sections for C.M.P. Arch Culverts3Jul/17
5.15.M3Dimension Details for C.S.P. Arch Culverts Dec/78
5.15.M4Coupler Widths and Types to be Supplied with Corrugated Steel Pipe Oct/78
5.15.M5Typical Formed-End C.S.P. Coupler Dec/78
5.15.M6Lock Seam on Helically Fabricated C.S.P. Dec/78
5.15.M7Standard C.S.P. Coupler Connection with Riveted Angle Bracket Dec/78

5.16 Drawings – Supply of reinforced concrete culvert

Drawing No.Drawing DescriptionRevision No.Date
5.16.M1Detail of Flared End Section for Reinforced Concrete Pipe Culverts1Jan/86

5.28 Drawings – Supply of flexible guide post traffic delineators

Drawing No.Drawing DescriptionRevision No.Date
5.28.M1  (Temporary)U-Channel Post Mounted Delineator (Galvanized Mild-Carbon Steel Type) Mar/98
5.28.M2Details of Pavement Edge Delineators (Renumbered from 3.11.M5) Oct/98

10.6 Drawing – Crack routing and sealing

Drawing No.Drawing DescriptionRevision No.Date
10.6.M1Typical Cross Sections Crack Routing and Sealing Asphalt Concrete Pavement Feb/95

Contact

Comments or enquiries can be directed to [email protected].