Division 20 – Common mechanical requirements

Section numberSection nameRevision date
20 00 13BMechanical General Requirements2010-12-01
20 00 23BMechanical Spare Parts and Maintenance Materials2010-12-01
20 01 05BMechanical Operation and Maintenance Data2021-03-31
20 01 05.01 Point Mnemonic Descriptions2008-06-02
20 01 06BMechanical Operation and Maintenance Manual2021-03-31
20 01 06.01 Operation & Maintenance Manual - Controls Section Outline2008-06-02
20 01 06.02 Point Mnemonic Descriptions2008-06-02
20 05 19BMeters2010-12-01
20 05 23BValves2010-12-01
20 05 25BPressure Gauges and Thermometers2021-03-31
20 05 29BHangers and Supports2010-12-01
20 05 43BIdentification for Mechanical Systems2012-07-01
20 05 48BVibration Isolation2010-12-01
20 15 00BTanks2010-12-01
20 15 00.01 Expansion Tank - Pneumatic Vessel2008-06-02
20 15 00.02 Glycol Fill Tank Pressure Vessel Type2008-06-02
20 15 00.03 Domestic Hot Water Storage Tank2008-06-02
20 15 00.04 Underground Fuel Storage Tank Fill Assembly2008-06-02
 20 20 10BPipe and Pipe Fittings2024-10-10
20 20 30BPiping and Equipment Insulation2021-03-31
20 20 40BExpansion Compensation2010-12-01
20 40 35BHot Water Specialties2010-12-01
20 40 38BSteam Specialties2010-12-01
20 40 40BRefrigeration Specialties2010-12-01

Division 21 – Fire suppression

Section numberSection nameRevision date
21 12 00BFire Suppression Standpipe and Hose System2015-11-30
21 13 13BWet Pipe Sprinkler System2017-09-25

Division 22 – Plumbing

Section numberSection nameRevision date
22 05 90BPlumbing Specialties2010-12-01
22 11 20BCleaning Domestic Water Systems2010-12-01
22 13 53BSeptic Tanks2010-12-01
22 13 53.01 Precast Concrete Septic Tank Syphon Chamber2008-06-02
22 13 53.02 Precast Concrete Septic Tank Pump Out Chamber2008-06-02
22 13 60BSanitary Sewage Disposal Field2010-12-01
22 13 60.01 Above Ground Sewage Field2008-06-02
22 13 60.02 Sewer Riser2008-06-02
22 13 60.03 Subsurface Sewage Disposal Field2008-06-02
22 13 65BSewage Holding Tanks2010-12-01
22 42 00BPlumbing Fixtures and Trim2010-12-01
22 51 19BCleaning and Chemical Treatment of Spa/Swimming Pools2010-12-01

Division 23 – Heating, ventilating and air conditioning

Section numberSection nameRevision date
23 01 30BDuct System Cleaning2010-12-31
23 07 00BDuctwork and Breeching Insulation2015-12-09
23 08 13BGeneral Mechanical Starting and Testing Requirements2021-03-31
23 08 23BMechanical Equipment Starting and Testing2021-03-31
23 08 33BMechanical Systems Starting and Testing2021-03-31
23 08 43BPressure Testing2021-03-31
23 08 83BBalancing and Adjusting of Mechanical Equipment and Systems2021-03-31
23 08 93BMechanical Equipment and Systems Demonstration and Instruction2021-03-31
23 08 95BEMCS Start-Up and Testing2020-05-12
23 09 10BControl Systems2019-06-05
23 09 23BEMCS General Requirements2020-05-12
23 09 24BEMCS Network Communications and System Configuration2022-09-09
23 09 25BEMCS Central/Portable Control Stations and Peripherals2022-09-09
23 09 26BEMCS Remote Control Units2022-07-29
23 09 27BEMCS Terminal Control Units2022-07-29
23 09 28BEMCS Field Work2020-05-12
23 09 29BEMCS Sensors, Devices and Actuators2020-05-12
23 09 30BEMCS Point Schedules2020-05-12
23 09 93BEMCS Control Sequences2020-05-12
23 10 10BService Station Fuel Dispensing System2010-12-31
23 25 01BCleaning and Chemical Treatment Equipment2021-03-31
23 25 01.01 Chemical Pot Feeder and Corrosion Coupon Rack2012-09-20
23 25 01.02 Installation of Chemical Pot Feeder, By-pass Filter, Corrosion Coupon Rack, and Sample Cooler2012-09-20
23 25 01.03 Installation of Chemical Metering System for Steam Boilers2013-03-19
23 25 01.04 Installation of Corrosion Coupon Rack, Chemical Metering System and Total Dissolved Solids Control System for Condenser Water System2012-09-20
23 25 01.05 Installation of Corrosion Coupon Rack, Chemical Metering System and Total Dissolved Solids Control System for Evaporative Condenser Water System2012-09-20
23 25 01.06 Packaged Steam Humidification System2013-03-19
23 25 02BCleaning and Chemical Treatment - General Requirements2013-04-04
23 25 13BCleaning and Chemical Treatment of Hydronic Systems2012-09-20
23 25 19BCleaning and Chemical Treatment of Steam Boiler Systems2013-04-04
23 25 20BCleaning and Chemical Treatment of Condenser Water Systems2012-11-09
23 25 26BCleaning and Chemical Treatment of Glycol Systems2012-11-09
23 31 13BDuctwork2021-03-31
23 31 30BDuctwork Accessories2010-12-31
23 37 10BAir Outlets2010-12-31
23 42 00BParticulate Air Filters2010-12-31
23 51 00BBreeching and Chimneys2010-12-31
23 57 00BHeat Exchangers2010-12-31
23 64 05BChiller Upgrading - Purge Unit and Pressure Relief Valve2010-12-31
23 81 05BVariable Speed Drives in Packaged Systems2010-12-31
23 82 10BCoils2010-12-31
23 84 93BCleaning and Chemical Treatment of Air Washer Re-circulating Humidifier Systems2010-12-31

Division 26 – Electrical

Section numberSection nameRevision date
26 01 10BElectrical Operation and Maintenance Data2022-07-04
26 01 11BElectrical Operation and Maintenance Manual2018-06-12
26 01 90BElectrical Spare Parts and Maintenance Materials2022-07-04
26 05 53Identification for Electrical Systems2022-07-04
26 08 10BElectrical Starting and Testing - General Requirements2022-07-04
26 08 20BElectrical Starting and Testing by Contractor2022-07-04
26 08 30BElectrical Starting and Testing by Contractor's Testing Agent2022-07-04
26 08 40BElectrical Equipment and Systems Demonstration and Instruction2022-07-04

Division 27 – Communications

Section numberSection nameRevision date
27 51 21BAddressable Decentralized Sound Masking Network2019-06-05

Publications

Contact

Connect with Technical Services and Procurement Branch:

Phone: 780-422-7456
Fax: 780-422-7479
Email: [email protected]