FIELD TEST PROCEDURES INDEX 1997 Edition

Note: The last 2 digits in the ATT Test number indicates the year of the last revision.

Table of Contents

Test Number Year Revised Test Name

ATT 3/95

BULK ASPHALT CONTENT, Part I, Truck Scale Weight Method

ATT 3/95

BULK ASPHALT CONTENT, Part II, Aggregate Totalizer Method

ATT 5/2022

CORING

ATT 6/95

DENSITY, Immersion Method, Waxed Asphalt Concrete Specimens

ATT 7/2022

DENSITY, Immersion Method, Saturated Surface Dry Asphalt Concrete Specimens

ATT 8/2022

DENSITY, In-Place Balloon Method

ATT 8S/2022

DENSITY, Calibration of Pressure Gauge (Supplement)

ATT 11/2022

DENSITY, In-Place Nuclear Method

ATT 12/2022

EXTRACTION, Part I, Reflux

ATT 12/2022

EXTRACTION, Part II, Centrifuge Method

ATT 12/2022

EXTRACTION, Part III, Correction Factor, Extracted Asphalt Content

ATT 13/2022

FORMING MARSHALL SPECIMENS, Field Method

ATT 14/2022

MOISTURE CONTENT, Open Pan Method

ATT 15/2022

MOISTURE CONTENT, Part I, Oven Method, Soil and Gravel

ATT 15/2022

MOISTURE CONTENT, Part II, Oven Method, Emulsified Asphalt Mixes

ATT 15/2022

MOISTURE CONTENT, Part III, Cutback Asphalt Mixes, Calcium Oxide Method

ATT 15/2022

MOISTURE CONTENT, Part IV, Microwave Oven Method

ATT 15/2022

MOISTURE CONTENT, Part V, Oven Method, Asphalt Concrete Mixes

ATT 16/95

PRODUCTION RATE AND PLANT CHECK, Part III, Drum Mix Asphalt Plants

ATT 16/95

PRODUCTION RATE & PLANT CHECK, Part IV, Drum Mix Recycle Asphalt Plant

ATT 16/04

ASPHALT RUBBER BLENDING EQUIPMENT, PRODUCTION RATE and PLANT CHECK, Part V, Drum Mix / Asphalt Rubber Plant

ATT 17/96

PLANT CALIBRATION, Part I, Drum Mix Asphalt Plants

ATT 17/96

PLANT CALIBRATION, Part II, Centre Feed Recycle Drum Mix Plants

ATT 19/2022

MOISTURE-DENSITY RELATION, Standard Compaction, +5000 m Material

ATT 20/2022

MOISTURE-DENSITY RELATION, One-Point

ATT 23/2022

MOISTURE-DENSITY RELATION, Standard Compaction, -5000 m Material

ATT 25/13

SIEVE ANALYSIS, Part I, 80 000 m Minus

ATT 25/13

SIEVE ANALYSIS, Part II - Pit Run Contamination, -5000 m Sieve

ATT 26/13

SIEVE ANALYSIS, 25 000 m Minus

ATT 27/95

SIEVE TEST, Seal Coat Emulsions

ATT 29/2022

SOILS IDENTIFICATION, Hand Method

ATT 30/95

TEMPERATURES

ATT 31/95

VISCOSITY, Zahn, Seal Coat Emulsions

ATT 32/95

VISUAL INSPECTION, Asphalt Concrete Formed Specimens

ATT 36/2022

VOID CALCULATIONS

ATT 37/2022

SAMPLING, Mixes

ATT 38/2022

SAMPLING, Gravel and Sand

ATT 42/21

SAMPLING, Asphalt

ATT 44/96

MOISTURE CONTENT, Speedy Moisture Teller

ATT 46/95

CALIBRATION OF AGGREGATE SPREADER

ATT 47/95

CALIBRATION OF ASPHALT DISTRIBUTOR

ATT 48/2022

CORRECTION FACTORS, Nuclear Moisture-Density Measurements

ATT 49/95

FLAKINESS INDEX

ATT 50/2022

PERCENT FRACTURES, Part I, Minus 20 000 m Aggregate

ATT 50/2022

PERCENT FRACTURES, Part II, Minus 80 000 m Aggregate

ATT 51/95

VISUAL INSPECTION, Asphalt Concrete Paving Mixtures

ATT 52/95

UNDISTURBED SAMPLING

ATT 53/06

SIEVE ANALYSIS, RAP

ATT54/96

DRY STRENGTH, Non-Plastic Aggregates

ATT 56/2022

RANDOM TEST SITE LOCATIONS, Part I, Granular Base Course

ATT 56/2022

RANDOM TEST SITE LOCATIONS, Part II, Stratified Random Test Sites for ACP

ATT 56/95

RANDOM TEST SITE SELECTION, Part III, Crack Sealing Operations

ATT 57/2022

REDUCING SAMPLES TO TESTING SIZE

ATT 58/96

DENSITY, Control Strip Method, GBC

ATT58A/93

DENSITY TEST, Control Strip Method, Granular Fill

ATT 59/99

SMOOTHNESS OF PAVEMENTS, Part I, Manual Profilograph

ATT 59/99

SMOOTHNESS OF PAVEMENTS, Part II, CS 8200 Profilograph

ATT 59/99

SMOOTHNESS OF PAVEMENTS, Part III, ES 2 000 Paveset Profilograph

ATT 60/95

SAMPLING, Slurry Seal Asphalt Mixes

ATT 61/95

AGGREGATE PROPORTIONING

ATT 64/96

MUSKEG TESTING, Bearing Value

ATT 65/96

EMULSION BREAKING POINT

ATT 66/96

DENSITY TEST, ASBC Control Strip Method

ATT 67/2022

PERCENT COMPACTION, Asphalt Concrete Pavement

ATT 68/96

APPEAL TESTING, Asphalt Content, Density and Gradation

ATT 70/96

ROUNDING OFF CALCULATED VALUES

ATT 71/95

SAMPLING SALT

ATT 72/96

SALT SIEVE ANALYSIS

ATT 73/95

CRACK SEALING, Measurement of Rout Cross-Section and Sealing

ATT 74/18

IGNITION ASPHALT CONTENT, Part I, Ignition Method

ATT 74/18

IGNITION ASPHALT CONTENT, Part II, Correction Factor

ATT 74/2022

IGNITION ASPHALT CONTENT, Part III, Correction Factor for RAP and Virgin Aggregate

ATT 75/04

SAMPLING RUBBER CRUMB

ATT 76/2022

INTER-LABORATORY REPEATABILITY TESTING

ATT 77/2022

THEORETICAL MAXIMUM SPECIFIC GRAVITY OF BITUMINOUS PAVING MIXTURES

Was this page helpful?

All fields are required unless otherwise indicated.

You will not receive a reply. Do not enter any personal information such as telephone numbers, addresses, or emails.

Your submissions are monitored by our web team and are used to help improve the experience on Alberta.ca. If you require a response, please go to our Contact page.