Non-urgent government operations are closed December 24 to January 1, reopening January 2. See the list of services available during this time.
Overview
A permit is required to install utility lines within the permitting area of a provincial highway. Public roads other than provincial highways are managed by municipalities.
Construction cannot take place without a valid permit.
Guidelines
The highway permit area for utility line installation varies depending on the highway classification:
Highway classification | Permit area |
---|---|
Freeways | 115 m from the centreline or 30 metres beyond the limit of the freeway, whichever is greater |
Multi-lane highways and major 2-lane highways | 60 m from the centreline or 30 m beyond the limit of the highway, whichever is greater |
Minor 2-lane highway | 50 metres from the centreline or 30 m beyond the limit of the highway, whichever is greater |
Installation procedures
Applicants should follow the following procedures for application and installation:
- electrical lines
- underground oil and gas pipeline
- underground water and sewer pipelines
- underground telecommunications cables
How to apply
Step 1. Consultation
The Alberta government may have plans to upgrade a provincial highway. Applicants should consult with us early in their planning process.
Step 2. Submit the application
Submit the application through the RPATH Portal.
It may take up to 30 business days for your application to be processed.
During construction
Ensure the following takes place:
- If lane closure or speed reduction is required, 511 Alberta must be notified at least 48 hours prior of the construction.
- A copy of the permit and Traffic Accommodation Strategy is always available for verification at the construction site.
- Only work covered by original permit is performed at the site.
- Any additional work, variation or change from the approval covered by the original permit requires additional or amended approval.
After construction
Upon completion of work activities, it is important to ensure that:
- all construction signs and materials are removed from the highway right-of-way
- the work site is restored to its pre-construction condition
- record drawings of the installation are submitted to the District Office
Contact
Connect with the district office for assistance on roadside development permits via RPATH Portal or Contact us.