The Foothills Medical Centre (FMC) is undergoing a power plant expansion to enhance the site's heating reliability.
This upgrade will also boost the facility's energy efficiency through cogeneration – a process that simultaneously produces electricity and heat. By integrating a new combustion turbine generator, FMC will not only improve its power generation capabilities but also decrease greenhouse gas emissions.
Project information
This project holds 2 key components:
- expanding the existing power plant with extra boiler capacity (and phasing out the temporary boiler)
- installing the turbine generator to increase cogeneration capacity
Together, these improvements will ensure a more sustainable and dependable energy supply for FMC.
For more detailed technical information, visit Foothills Medical Centre Power Plant Upgrade & Cogeneration Initiative – Alberta Major Projects.
Subscribe for updates
Use the following form to subscribe and unsubscribe from our mailing list.
Construction activities
The Foothills Medical Centre (FMC) power plant upgrade is currently in progress and is expected to be completed in 2025.