Important dates
Development permit appeals must be filed within 21 days of the date of the decision by the development authority or the 40-day processing time limit expiring, unless the municipality and the applicant have an extension agreement in place.
Overview
Development permit appeals challenge the decision of a development authority regarding the approval or refusal of a development permit application. Appeals are heard by local Subdivision and Development Appeal Boards (SDABs) or by the Land and Property Rights Tribunal (LPRT) where the application relates to matters of provincial interest. There are independent bodies that provincial and municipal governments do not direct in their decisions.
For more information, see Development Permit Appeal Process.
Eligibility
Appeals can only be filed by those who are materially affected by an application when the provisions of the land use bylaw have been relaxed, varied, or misinterpreted.
File an appeal
Step 1. Apply for an appeal
Appeal forms can be found on the website of your local SDAB or the LPRT. Appeal applications must provide the reasons for appeal and include payment for any applicable fees. Municipalities will have a fee schedule and require applicants to fill out appeal forms or submit letters of appeal.
Step 2. Attend the hearing
The SDAB or LPRT will arrange a hearing within 30 days of receiving the appeal application. At least 5 days in advance of the hearing, written notice of the hearing must be provided to:
- the appellant
- the applicant (if different from the appellant)
- the development authority whose order, decision or development permit is the subject of the appeal
- owners required to be notified under the provisions of the land use bylaw, and
- any other party that the SDAB considers to be affected by the appeal
The MGA specifies that the SDAB or LPRT is required to hear from any person or agency notified and any other person who claims to be affected by the order, permit or decision on the application.
Step 3. Hearing process
Typically, a hearing includes a presentation from the development authority explaining the original decision and a presentation from the appellant. These presentations are followed by presentations from any other parties to the appeal.
In making decisions, the SDAB and LPRT must act in accordance with regional plans and policies, statutory plans, and any land use bylaw in effect. The SDAB or LPRT is required to consider the Matters Related to Subdivision and Development Regulation but are not bound them.
Step 4. After the hearing
The SDAB or LPRT may confirm, revoke, or amend the original decision on the application and must issue a decision with reasons to the appellant in writing within 15 days after the hearing has been concluded. Until the decision is issued in writing, it is not official and cannot be acted upon.
Additional appeals
SDAB or LPRT decisions can be appealed to the provincial Court of Appeal, but only on a question of law or jurisdiction. To do so, appellants must be able to show that errors were made in the appeal process in terms of procedure or process. For example, a failure to provide proper notice as required in the MGA, or refusal to provide due process in the hearing may be the basis for an appeal to the court.