Public input in the approval process

Under the Energy, Environment and Utilities Statutes Amendment Act, 2026, if passed, the Alberta Utilities Commission (AUC) would become the primary provincial regulator for data centres of 10 megawatts and larger. Data centres smaller than 10 megawatts would continue to be approved by municipalities. The steps below are where decision-makers must consider public input and where people can appeal.

Formal participation steps

StepWhat it involvesTiming
Municipal public hearing for rezoningIf rezoning or a change to a municipal land-use plan is required, the public may provide input at a hearing before council makes its decision.Before second reading of the bylaw.
Development-permit appealWhere existing zoning allows the project, eligible affected parties may appeal the municipality’s development-permit decision. For a permitted use, an appeal is allowed only if the bylaw was relaxed, varied or misinterpreted.Within 21 days of the written decision.
Alberta Utilities Commission (AUC) Participant involvement programThe proponent must contact potentially affected residents, landowners, municipalities and Indigenous groups. Project design can still change at this stage. This currently applies to power plant applications and would also apply to data centres should Bill 42 pass.Before the application is filed
AUC Statement of intent to participateA person seeking to participate files through the AUC’s eFiling System and explains how the proposed facility may directly and adversely affect their rights or interests.By the date in the public notice
AUC hearing, if heldThe AUC determines whether a hearing is required. Eligible participants may submit evidence and participate in the proceeding.According to the AUC proceeding schedule
Statement of concern for an environmental or water approvalA directly affected person may submit written concerns to Alberta Environment and Protected Areas about an application under the Environmental Protection and Enhancement Act or Water Act. Failure to file may affect later appeal rights.For a Water Act licence or an environmental approval: within 30 days of the last public notice. For a Water Act approval: within 7 days. The notice may allow longer.
Notice of appeal for an environmental or water decisionFiled with the Environmental Appeals Board by directly affected parties. The Board refers most appeals to mediation.Within 30 days of receiving notice of the decision. Within 7 days for a Water Act approval, an enforcement order or an environmental protection order.