AI data centres and land use
Alberta’s government is proposing changes that would restrict data centres 10 megawatts or larger from being built within 600 metres of the nearest home or on Alberta’s highest-quality farmland, as well as on currently irrigated land.
Land Restrictions
The 600 metres would be measured from the edge of the project site. The farmland protection would cover Class 1 and 2 agricultural land, as well as Class 3 land in municipalities without Class 1 or 2 land.
Smaller data centres would continue to be approved through existing municipal land-use processes.
Projects that already have an AUC decision or active review, a signed AESO grid agreement or a municipal development permit when the rules take effect would continue under existing rules. The rules would also not apply in Designated Industrial Zones, on brownfield sites or at existing power plant sites. A proponent may reach an agreement with an affected landowner whose dwelling is within the 600 metre setback. If the AUC validates the agreement, the project may proceed within the setback. For stand-alone data centres from 10 megawatts to under 75 megawatts with no on-site generation, a municipality could as the AUC for an alternative setback where local planning supports compatible development.
Land that could be irrigated in future would need an irrigation assessment first.
It is also important to note that foreign-controlled corporations cannot own more than two parcels totalling 20 acres of privately owned land outside urban municipalities, unless an exemption in the Foreign Ownership of Land Regulations or an Order in Council applies.
Health and safety protections for people in Alberta
Data centres are subject to the same health and safety requirements as other large industrial facilities.
Alberta’s government requires data centres to follow sound and lighting controls, manage cooling fluids under environmental rules and immediately report any incidents that may occur.
Noise and light
Data centres would need to meet the AUC's noise rule (Rule 012), which already applies to power plants. Their lighting would also be assessed as part of the AUC's review. Proposed setbacks would work with existing noise rules so nearby residents are protected by both a minimum distance and requirements addressing project-specific noise. They would also need to:
- comply with local noise bylaws and lighting requirements that apply to all industrial sites.
- meet the noise limits, using sound barriers or enclosed equipment where needed
- conduct noise studies and add sound controls where required by the AUC
Waste heat
Data centres of 10 megawatts or larger would need to be designed and operated so their excess heat can be recovered and made available for greenhouses, industry or homes. They would not have to find a user for the heat.
Cooling system safety
- When cooling equipment is serviced or replaced, used materials are sent to approved waste treatment facilities.
- Companies must report a release that may harm the environment as soon as they know or ought to know of it, and clean it up, under the Environmental Protection and Enhancement Act.