AI data centres and electricity

Alberta’s rules are designed to protect the reliability and affordability of electricity that Albertans, businesses and communities depend on.

Electricity Protections

  • Data centres must show they will not put grid reliability at risk before the Alberta Electric System Operator (AESO) approves a connection.
  • Data centres pay for their own electricity and do not receive discounted electricity rates. This includes paying for their own system connection fees and any use of the Alberta grid, which is expected to lower transmission costs shared by all ratepayers.
  • Power for homes and essential services comes first. In an emergency, data centres are already required to reduce their electricity use first, before any other user.

Data centres and power generation

Alberta encourages data centres to build their own power generation. This reduces the draw on the shared grid and helps keep it reliable. Through the Utilities Statutes Amendment Act, 2025, projects that bring their own power supply are prioritized.