Overview
The Calgary Radiopharmaceutical Centre (CRC) will be home to Calgary’s first and Alberta’s third cyclotron. This new facility will support the treatment of diseases including cancer, cardiac, and neurological conditions.
The Development Permit for the facility was approved by the City of Calgary marking a significant milestone for the Project (DP2024-07321).
The facility design is finalized and was submitted to the Canadian Nuclear Safety Commission (CNSC) for approval in April 2025. This application will ensure the federal requirements for housing the cyclotron within this type of facility are followed. Construction of CRC is anticipated to be complete by Fall 2027. Following the completion of construction, internal commissioning and green space reclamation activities will begin.
Project updates
June 2025
The Infrastructure Ministry continues to work with the CNSC to secure the necessary permits for the facility.
Work has begun on site including fencing the project area, removing vegetation, fibre line and water line relocations, site grading, the removal of retaining wall, shoring and excavation. Construction will continue into the summer months and we encourage you to sign up for project email notices to stay informed as we move through construction.
Throughout the project Hospital Drive NW will be closed at the project site. For everyone’s safety, we kindly ask all those in the area to observe posted signage. Your cooperation helps ensure the well-being of both the public and staff working on the project.
To ensure the facility complies with federal regulations, an air dispersion modeling report was completed. The report found the new facility would pose no risk to residents in the area. The report found the new facility would pose no risk to residents in the area. Read the air dispersion model report.
Get informed



For additional details:
Radiopharmacy
A radiopharmacy is a specialized facility that handles and dispenses radioactive materials.
Cyclotron
A cyclotron is a machine within the radiopharmacy that will produce the radioactive isotopes used within Foothills Medical Centre (FMC).
Facility safety
Cyclotrons adhere to stringent safety regulations enforced by the Canadian Nuclear Safety Commission (CNSC). The facility incorporates multiple safety layers, including shielding, containment, and operational monitoring.
Safety begins with the facility's design, including concrete walls which will be approximately 2.0 meters (~7 feet) thick. The facility employs a sophisticated radiation monitoring system including detectors, handheld survey meters, and contamination meters, to prevent accidental removal of radioactive material.
A containment system prevents the release of radioactive gases into the atmosphere, and they are held until they decay into non-radioactive elements. For more information about safety regulation visit CNSC.
Alberta Health Services (AHS) is responsible for the public disclosure of any incidents that may occur on site through operation of this facility. To view the notification and disclosure requirements, visit AHS Cyclotron Public Disclosure.
Facility design
The Ministry of Infrastructure worked closely with architects and engineers to finalize the facility layout.
Changes have been made throughout the design process to address safety, operational requirements, and lessons learned from a similar facility in Edmonton and to address cost savings.
The size of the building meets operational needs while considering available space, safety and cost.
Facility operation
The facility will be operated by AHS and utmost care will be undertaken by Foothills Medical Centre Staff to ensure its safe operations.
Construction process
Site preparation, planning, and investigations are underway. Work will be undertaken in three main stages.
- Stage 1 (Complete) – Site preparation and demolition: Fencing has been installed at site. This stage requires levelling of the site and will involve the removal of soil, an existing retaining wall, relocation of fibre and water lines, and trees to prepare the site for building construction.
- Stage 2 (Underway) – Site grading, earthworks and shoring to prepare for building construction. This will include an increase in construction activities at site and will require closure of Hospital Drive NW just south of the site to be closed to motorists but will remain open to pedestrians.
- Stage 3 – CRC Facility: Now that the Development/Building Permit has been received and the design approval for the cyclotron is with the Canadian Nuclear Safety Commission, construction of the physical building is anticipated to begin summer 2025.
Construction impacts
Construction activities may cause short-term impacts to the neighbouring community. Our team will endeavour to minimize those impacts where possible.
If you have any questions or concerns during construction, please do not hesitate to reach out to the project team at 1-888-989-8810 or by email [email protected].
Sign up for updates
Complete the form below to sign up for project updates.
CRC project survey
To help us improve our materials and the information we share, take 2 minutes to complete our project survey.